Solar PV in Wisconsin
Which codes apply? In Wisconsin, solar PV systems fall under the 2023 NEC, the state’s own code in place of the IRC, the 2021 IBC, and NFPA 1 in place of the IFC.
Codes that reach solar PV systems
The edition Wisconsin enforces for each code that governs the product, and the part of the code that does.
-
NECNational Electrical CodeThe Wisconsin NEC record2023 NECVerified
in force since Sep 1, 2026
Where it reaches the product. Article 690, solar photovoltaic systems, with 705 for the interconnection and 690.12 for rapid shutdown.
Wisconsin electrical code (ch. SPS 316) · Wis. Admin. Code ch. SPS 316 (NEC edition listed in s. SPS 316.007(1)(a)); Clearinghouse Rule CR 26-016 (Register June 2026 No. 846)
-
IRCInternational Residential CodeThe Wisconsin IRC recordState’s own codeVerified
Where it reaches the product. Section R324, solar energy systems.
Wisconsin Uniform Dwelling Code (UDC) · Wis. Admin. Code chs. SPS 320-325
The next IRC edition is in development.
-
IBCInternational Building CodeThe Wisconsin IBC record2021 IBCVerified
in force since Sep 1, 2025
Where it reaches the product. Rooftop structures and the structural load of the array.
Wisconsin Commercial Building Code (chs. SPS 361-366) · Wis. Admin. Code chs. SPS 361-366 (Clearinghouse Rule CR 23-007, identified from the Legislature’s document naming)
-
IFCInternational Fire CodeThe Wisconsin IFC recordAnother model codeVerified
Where it reaches the product. Chapter 12, section 1205, solar photovoltaic power systems and roof access.
Wisconsin Fire Prevention Code (ch. SPS 314, NFPA 1) · Wis. Admin. Code ch. SPS 314
The 2024 IFC is in development.
Wisconsin laws that name solar PV systems
On the site: two laws, rules, orders, and bills, newest first.
| Law or rule | Kind | Stage | Date | What it does |
|---|---|---|---|---|
| PSC Application Filing Requirements: Solar Energy Projects | Agency guidance | PartialIn force | Oct 1, 2025 | Lists what large solar projects must file, including setbacks, inverter details, decommissioning plans and costs, and plans for any co-located battery storage. Source (opens in a new tab) |
| Wis. Stat. 196.491 | Statute | PartialIn force | – | Requires a state certificate of public convenience and necessity before a large electric generating facility is built. Source (opens in a new tab) |
For information only. Your local building or fire official decides which code applies. We check state records often but can miss a recent change, so confirm with your official before you design, permit, or install. Terms of use