Commercial and utility energy storage systems in Wisconsin
Which codes apply? In Wisconsin, commercial and utility energy storage systems fall under the 2023 NEC, NFPA 1 in place of the IFC, the 2021 IBC, and the 2020 NFPA 855 through the fire code.
Codes that reach commercial and utility energy storage systems
The edition Wisconsin enforces for each code that governs the product, and the part of the code that does.
-
NECNational Electrical CodeThe Wisconsin NEC record2023 NECVerified
in force since Sep 1, 2026
Where it reaches the product. Article 706, with 705 for the interconnection.
Wisconsin electrical code (ch. SPS 316) · Wis. Admin. Code ch. SPS 316 (NEC edition listed in s. SPS 316.007(1)(a)); Clearinghouse Rule CR 26-016 (Register June 2026 No. 846)
-
IFCInternational Fire CodeThe Wisconsin IFC recordAnother model codeVerified
Where it reaches the product. Chapter 12, section 1207, and the operational permit.
Wisconsin Fire Prevention Code (ch. SPS 314, NFPA 1) · Wis. Admin. Code ch. SPS 314
The 2024 IFC is in development.
-
IBCInternational Building CodeThe Wisconsin IBC record2021 IBCVerified
in force since Sep 1, 2025
Where it reaches the product. Occupancy, construction type, and separation for the building that holds the system.
Wisconsin Commercial Building Code (chs. SPS 361-366) · Wis. Admin. Code chs. SPS 361-366 (Clearinghouse Rule CR 23-007, identified from the Legislature’s document naming)
-
NFPA 855NFPA 855, Standard for the Installation of Stationary Energy Storage SystemsThe Wisconsin NFPA 855 record2020 NFPA 855Verified
in force since Sep 1, 2025 · Through the IFC, chapter 12 · Edition derived from the fire code the state adopts
Where it reaches the product. The whole standard: siting, size and separation, fire control, explosion control, and commissioning.
Wisconsin Commercial Building Code, which applies 2021 International Fire Code section 1207 to commercial buildings · Wis. Admin. Code SPS 361.03(14)
The 2023 NFPA 855 is in development.
Wisconsin laws that name commercial and utility energy storage systems
On the site: seven laws, rules, orders, and bills, newest first.
| Law or rule | Kind | Stage | Date | What it does |
|---|---|---|---|---|
| Wis. Admin. Code ch. SPS 316 | Code amendment | PartialIn force | Sep 1, 2026 | Adopts the 2023 National Electrical Code with state changes for electrical work from Sep 1, 2026, replacing the 2017 edition. Source (opens in a new tab) |
| Kenosha County storage moratorium | Local ordinance | PartialIn force | May 19, 2026 | Pauses county review of new battery energy storage system permits and zoning approvals for 12 months from a May 19, 2026 vote. Source (opens in a new tab) |
| Fire code review scope statement | Rule | PartialPending | Nov 4, 2025 | Starts a rulemaking to update the state fire prevention code, which now references the 2012 edition of NFPA 1. The department may adopt the 2024 edition. Source (opens in a new tab) |
| PSC Application Filing Requirements: Solar Energy Projects | Agency guidance | PartialIn force | Oct 1, 2025 | Lists what large solar projects must file, including setbacks, inverter details, decommissioning plans and costs, and plans for any co-located battery storage. Source (opens in a new tab) |
| Storage project filing requirements | Agency guidance | PartialIn force | – | Lists what storage projects seeking state approval must file. Source (opens in a new tab) |
| Wis. Admin. Code ch. NR 673 | Rule | PartialIn force | – | Lets handlers manage hazardous waste batteries, such as lithium and lead-acid batteries, under the universal waste rules in ch. Source (opens in a new tab) |
| Wis. Stat. 196.491 | Statute | PartialIn force | – | Requires a state certificate of public convenience and necessity before a large electric generating facility is built. Source (opens in a new tab) |
Every Wisconsin law on commercial and utility energy storage systems, with filters
For information only. Your local building or fire official decides which code applies. We check state records often but can miss a recent change, so confirm with your official before you design, permit, or install. Terms of use