ERCOT Nodal Operating Guide Revision Request 245
Partial
What does Texas ERCOT Nodal Operating Guide Revision Request 245 do? Requires inverter-based resources and certain wind resources in ERCOT to meet voltage and frequency ride-through requirements consistent with or exceeding IEEE 2800-2022.
Facts
- Kind
- Tariff
- Status
- In force
- Stage
- In force
- Signed or decided
- October 1, 2024
- Effective
- October 1, 2024
- Topics
- Interconnection
- Products
- Source
- Electric Reliability Council of Texas (opens in a new tab)
- Citation
- Market rules page for NOGRR 245
The state’s codes
The codes that reach each product this law names, with the edition Texas is on. Each links to the record.
For information only. Your local building or fire official decides which code applies. We check state records often but can miss a recent change, so confirm with your official before you design, permit, or install. Terms of use