What does Oregon OPUC Order No. 24-448 do? Approves the three investor-owned utilities' small generator interconnection agreements, with changes. Nameplate rating for inverter-based units is the inverter's AC output rating. Customers with utility power purchase agreements may match the interconnection agreement term to that contract.

Facts

Kind
Commission order
Status
Adopted
Stage
In force
Signed or decided
December 19, 2024
Effective
December 19, 2024
Topics
Interconnection
Products
Source
Public Utility Commission of Oregon (opens in a new tab)
Citation
Order No. 24-448

For information only. Your local building or fire official decides which code applies. We check state records often but can miss a recent change, so confirm with your official before you design, permit, or install. Terms of use