What does Oregon OPUC Docket AR 688 do? Proposes updates to the small generator interconnection and net metering rules. Order No. 26-368 opened the formal rulemaking on Sep 30, 2026. Proposed changes include study deadlines, lower costs for late studies, and quarterly utility reporting.
Facts
- Kind
- Rule
- Status
- Proposed
- Stage
- Pending
- Signed or decided
- September 30, 2026
- Topics
- Interconnection, Tariffs and bill credits
- Products
- Source
- Public Utility Commission of Oregon (opens in a new tab)
- Citation
- Docket AR 688