OPUC Docket AR 659
Partial
What does Oregon OPUC Docket AR 659 do? Adopted 2024 changes to the net metering and small generator interconnection rules. The changes move inverter requirements to IEEE 1547-2018 and UL 1741 SB, and add export control rules for projects with storage.
Facts
- Kind
- Commission order
- Status
- Adopted
- Stage
- In force
- Effective
- April 9, 2024
- Topics
- Interconnection, Tariffs and bill credits
- Products
- Source
- Public Utility Commission of Oregon (opens in a new tab)
- Citation
- Docket AR 659 hearings report