SB 228 (2025); MCA 15-70-801 to 805 public charging station requirements
Lead only
What does Montana SB 228 (2025); MCA 15-70-801 to 805 public charging station requirements do? Public stations above 25 kW must register with MDT within 30 days, post rates and install meters; legacy stations must add vehicle-delivery metering by 2028; 3 cents/kWh tax. Home and HOA chargers exempt. public chargers.
Facts
- Kind
- Statute
- Status
- Enacted
- Stage
- In force
- Effective
- July 1, 2025
- Topics
- Charger standards and consumer rules
- Products
- Source
- afdc.energy.gov (opens in a new tab)
The state’s codes
The codes that reach each product this law names, with the edition Montana is on. Each links to the record.
For information only. Your local building or fire official decides which code applies. We check state records often but can miss a recent change, so confirm with your official before you design, permit, or install. Terms of use