What does Massachusetts St. 2024, c. 239, § 74 do? Requires large clean energy facilities, including storage of 100 MWh or more, to get one consolidated permit from the Energy Facilities Siting Board. The board must decide within 15 months. Smaller solar and storage facilities may seek a board permit or a new state review of local decisions.
Facts
- Kind
- Statute
- Status
- In force
- Stage
- In force
- Topics
- Fire protection and siting, Permitting
- Products
- Source
- Massachusetts Legislature (opens in a new tab)
- Citation
- St. 2024, c. 239, § 74 (G.L. c. 164, §§ 69T-69W), with definitions in §§ 50-58 (G.L. c. 164, § 69G)
The state’s codes
The codes that reach each product this law names, with the edition Massachusetts is on. Each links to the record.
For information only. Your local building or fire official decides which code applies. We check state records often but can miss a recent change, so confirm with your official before you design, permit, or install. Terms of use