What does Arkansas Arkansas PSC Docket 22-026-TF Order 8 (utility EV charging deployment) do? Investor-owned utilities may own public DC fast chargers; must let site hosts install meters to measure electricity sold, use pre-qualified vendors, and file annual reports. public chargers.
Facts
- Kind
- Commission order
- Status
- In force
- Stage
- In force
- Topics
- Charger standards and consumer rules
- Products
- Source
- afdc.energy.gov (opens in a new tab)